Tuesday, 22 July 2014

Test Status Report - Template and Walkthrough

As mentioned in the End of Day Reporting - Worked Example article, EoD reporting is something we'll get asked to do as software testers, on virtually all our projects. In fact it should be literally all our projects, even when we're not asked we should provide it.

In order to do so, we need a means to capture the data that will be included in a report. That data is just data though and we need to convert it into easily digestible information. Be mindful that raw numbers may be accurate and are valuable, but they are often devoid of meaning. When reporting, don't be shy about including context and narrative - your report may be unreadable without it!

The previous article on End of Day reporting covered some points around presentation, so let's look at capturing and interpreting the raw data here. When reading through this article, have a copy of the template open in front of you. We'll walk-through each of the key sections here, but it's best to watch the YouTube video and refer to the template for a more in depth look at the Workbook.

Get a copy of the Test Status Tracker Template



YouTube Channel: [WATCH, RATE, SUBSCRIBE]

Oh, watch out for formulas, there are plenty of them on the Worksheets!

--------------

Project Details
Enter the following details about the application. This data is used throughout the Workbook.

Project Name: [Enter the name of the project or application under test]
Start Date: [Enter the date as nn-mmm, e.g. 21-Jul]
Total No of Cases: 
[Enter the total Test Cases in scope]

Daily Tracker
There is nothing you need to enter on this tab. It is generated from the Data Table and Issue Tracker tabs. However, you will need to manually edit chart symbol colours. Refer to the status table and review variance against plan on the chart. You'll then need to select the individual data point on the green Actual line, then fill the correct colour into the point.

Data Table
There are two main sections, Planned and Actual, where you need to enter data. Before completing the table, enter the names of the testing staff in the left hand column. When planning out the amount items that will be worked on each day, enter the total in the above 'Total No. Of Test Cases' box first. Then map out what can be delivered on a day by day basis, for each member of staff.

At the end of each day, enter the Actual numbers achieved by each team member.
With the data in place you will need to select the calculation cells at the bottom of the 'Actual' table and using the fill handle, populate the cells under the day you have just entered data for


This is done daily to avoid showing zero figures on the chart, making progress easier to see.

Issues Tracker
Where an issue or risk emerges during delivery, track it on this tab if your project has no other central place to record the data.

Downtime Tracker
Each time the team are unable to progress with delivery due to some issue, this is 'downtime' and should be recorded on the Downtime Tracker tab.

The tracker forms a historic record of time lost and allows reconciliation of lost time against plan, to support reporting and re-scheduling activities.

--------------


As stated above, watch the video for a clearer run-down of the tracker. This is one worked example to show some tricks and tips of how you can make your own. If you make any interesting changes be sure to let us know!

Mark



Liked this post?





0 comments: